Uniform darkening of all phases
Possible causes:
- prolonged overload;
- insufficient cooling;
- high ambient temperature;
- frequent starts;
- low-speed operation without independent ventilation;
- an incorrectly selected thermal protection model.

Stator rewinding is the comprehensive restoration of an electric motor winding, preserving — or deliberately and justifiably changing — its electromagnetic, thermal and mechanical characteristics.
Proper rewinding is not simply a matter of removing the burnt-out wire, winding coils of roughly the same size and connecting them to the terminal box.
The following must be precisely reproduced or confirmed by calculation:
A mistake at any of these stages can result in the motor, after repair:
That is why professional stator rewinding should begin not with manufacturing new coils, but with diagnosing the cause of the failure and precisely recovering the original winding data.
To rewind an electric motor stator, you need to:
The stator winding is a system of electrically connected conductors placed in the slots of the stator core.
When voltage is applied, it produces a rotating magnetic field that interacts with the rotor and generates electromagnetic torque.
The winding parameters determine:
The winding is therefore not a set of independent coils. It is part of a single electromagnetic system together with the core, the air gap and the rotor.
Rewinding may be necessary in the case of:
Rewinding is not always necessary in the case of low insulation resistance. If the cause is only moisture or surface contamination, cleaning, drying and re-impregnation are sometimes enough.
A local repair may be worthwhile if:
Examples:
A local repair must not be used to mask an interturn short circuit inside a slot, or general thermal ageing of the winding.
Before repair, the condition of the whole machine must be assessed.
Rewinding may not be worthwhile if:
For a large, high-voltage, special-purpose or imported motor, rewinding often remains economically justified even when the scope of work is considerable.
Two windings can look almost identical from the outside yet have different characteristics because of differences in:
When rewinding, it is important to reproduce not only the mass of copper but also its correct electrical and spatial arrangement.
One common mistake is selecting the wire based solely on the measured diameter of the old conductor.
This is unreliable because:
What must be determined is the total electrical copper cross-section, not just the outer dimension of the insulated conductor.
Increasing the wire cross-section without changing the number of turns and the geometry can lead to:
More copper does not always mean a more reliable winding. What matters is the right balance between copper, insulation, mechanical strength and cooling.
Before starting work, the following are recorded:
The following are photographed:
Before removing the winding, the probable cause of its failure must be established.
It is necessary to establish:
Without eliminating the root cause, the new winding may fail again.
Possible causes:
Possible causes:
Possible causes:
Possible causes:
Possible causes:
Possible causes:
If the condition of the winding allows, the following are carried out before it is removed:
These results help to determine:
This is one of the most critical stages.
Before removing the old winding, the following must be recorded:
The number of poles can be determined from:
The synchronous speed depends on the supply frequency and the number of pole pairs:
nₛ = 60 · f / p
where:
The actual speed of an asynchronous motor is lower than the synchronous speed because of slip.
An error in determining the number of poles completely changes the speed and the operating mode of the motor.
The coil pitch is the number of slot divisions between the two sides of one coil.
It can be:
The pitch affects:
The pitch must not be chosen merely for the convenience of laying the coils.
For a three-phase winding, this parameter is given by:
q = Z / (2p · m)
where:
This value helps to determine the type and distribution of the winding.
For fractional-slot windings, q is not a whole number, so the diagram requires especially precise reproduction.
The number of turns is determined:
It is advisable to count the turns in several coils from different phases.
A final conclusion must not be drawn from a single, partially burnt coil.
During a previous repair, someone may have:
The old winding therefore cannot automatically be treated as the factory reference.
Its data must be compared with:
It is necessary to determine:
The diagram must not just be described in words — it must also be drawn.
One and the same phase winding can have different line parameters depending on the connection scheme.
In a star connection:
In a delta connection:
An incorrect connection can cause:
The data sheet must contain:
| Parameter | Value |
|---|---|
| Motor type | — |
| Power | — |
| Voltage | — |
| Frequency | — |
| Current | — |
| Speed | — |
| Number of slots | — |
| Number of poles | — |
| Number of phases | — |
| Type of winding | — |
| Number of layers | — |
| Coil pitch | — |
| Number of coils | — |
| Coils per group | — |
| Turns per coil | — |
| Conductors per turn | — |
| Wire size | — |
| Parallel branches | — |
| Connection diagram | — |
| Mass of copper | — |
| Slot insulation | — |
| Phase-to-phase insulation | — |
| Wedge type | — |
| Impregnation system | — |
| Sensor positions | — |
| Lead marking | — |
The data sheet is accompanied by:
Before removal:
Depending on the design, the following are used:
The main task is to remove the winding without damaging:
Excessive heating of the core can cause:
After such damage, the new winding may operate with an elevated current and overheat, even though its own insulation is sound.
The temperature regime during removal must be controlled in line with the materials and the technology of the specific facility.
It is not permitted to:
After removal, the following are removed:
Cleaning is carried out so as not to create:
After cleaning, the slots are inspected under adequate lighting.
Before fitting the new winding, the serviceability of the core must be confirmed.
The following are checked:
A magnetic flux is set up around the core and its heating is monitored.
The method helps to reveal:
The following are monitored:
Simply heating the core without controlling the magnetic regime does not give a comparable result.
Systems that detect currents between damaged laminations at a relatively low magnetic flux may be used (for example, EL CID-type methods).
Advantages:
Limitations:
For critical machines, it is advisable to combine different types of testing.
Depending on the defect, the following may be used:
After repair, the core must be re-tested.
The following are checked:
Rewinding does not correct mechanical deformation of the stator. If the geometry is out of tolerance, an uneven air gap can result after assembly.
The insulation system is not a single material but a compatible set:
The materials must be mutually compatible in terms of:
The insulation class characterises the permissible temperature resistance of the material system.
However, the insulation class does not mean that the motor should constantly operate at the maximum permissible temperature of that class.
The actual service life depends on:
Using a higher-class material does not compensate for:
The thickness is determined by:
Insulation that is too thin may fail to provide adequate electrical and mechanical strength.
Insulation that is too thick:
For high-voltage machines, the following are critical:
Such coils are usually manufactured as form-wound sections with multi-layer insulation.
Low-voltage motor repair methods cannot automatically be carried over to a high-voltage machine.
When supplied from a converter, the winding is subjected to:
The following may be required:
Coils are manufactured on formers or on special winding equipment.
Before winding, the following are determined:
The former must ensure:
A coil that is too large:
A coil that is too small:
The tension must be:
Uneven tension can lead to:
During winding, the following must be ensured:
If one of the parallel conductors has a weak connection or an open circuit, the overall phase resistance may change only slightly, but the local overheating will be significant.
For large and high-voltage machines, coils may be manufactured as rigid, form-wound sections.
The process includes:
Such coils must precisely match the slots and the end-winding zone of the specific stator.
Before laying, the following are checked:
If necessary, the following are performed:
A coil defect is far easier to correct before the coil is laid into the stator.
The slot insulation must:
Particular attention is paid to:
At the slot exit, the winding is subjected to:
For protection, the following may be used:
With insufficient protection, this area often becomes the site of a breakdown.
Laying is carried out in the sequence defined by the winding diagram.
The following must be checked:
For low-voltage machines, soft coils are often used, formed and laid either by hand or with mechanised equipment.
A typical sequence:
The use of sharp metal tools without insulating protection must be avoided.
Form-wound sections are fitted with checks of:
Damage to the surface protective layer can lead to partial discharges even without a direct breakdown.
It is not permitted to:
The slot must accommodate:
An excessive fill factor leads to:
Too low a fill factor allows the conductors to move under electromagnetic forces.
In a two-layer winding, insulation is fitted between the top and bottom layers that:
Between phases in the end-winding region there must be a reliable insulating clearance or special separators.
Particularly important locations are:
Slot wedges hold the conductors inside the slots.
They must provide:
The following are checked:
Loosening of the wedges can lead to:
Overly tight wedges are also dangerous, since they can damage the insulation or deform a tooth.
The end-turns must:
The geometry is checked with templates and measurements.
The main causes:
The end-turns must therefore be not only electrically insulated but also mechanically engineered.
Connections are made in accordance with the diagram.
Methods:
Every connection must have:
During soldering, the following are checked:
A connection subject to significant mechanical loads must not rely on the solder alone to hold it together.
Welding can provide a reliable contact, but it requires control of:
Excessive heating can damage the insulation of adjacent areas.
Once the contact is made, it is insulated with a system that matches:
The following must not be left:
The leads must be:
The marking must match the diagram and the documentation.
After assembly, the following are checked for consistency:
If the design includes temperature sensors, they are fitted:
Before and after impregnation, the following are checked:
A sensor mounted too far from the conductors may show the temperature with a delay, or read it too low.
The bandages and cords must:
Bandaging is carried out at the specified locations with controlled tension.
Excessive tension can deform the coils. Insufficient tension will not provide adequate mechanical strength.
Before impregnation, the most thorough possible checks are carried out, because correcting mistakes after curing will be difficult.
The following are checked:
An incorrectly connected group can produce a magnetic field opposing the other groups.
Consequences:
Polarity is checked using special methods before impregnation and before applying full voltage.
The phase resistance is measured with a precision instrument.
A four-wire (Kelvin) method is advisable, especially for low-resistance windings.
The following must be recorded:
Asymmetry can indicate:
The surge test compares the response of the windings to a short high-voltage pulse.
It can help to reveal:
Limitations:
Before impregnation, the winding is often dried to remove:
Moisture inside the winding can:
The temperature and the insulation resistance are monitored.
Impregnation simultaneously performs an electrical, mechanical, thermal and protective function.
It must:
The stator is dipped into the impregnating material.
Advantages:
Limitations:
The material is metered onto the winding, sometimes while it is rotating and heated.
Advantages:
Limitations:
Air is removed from the winding, after which varnish or resin is introduced.
Advantages:
Limitations:
After evacuation, the material is fed in under pressure.
Advantages:
Limitations:
The following are taken into account:
A system that is too rigid can crack under thermal cycling. One that is too soft will not hold the winding adequately.
The following are checked:
Using expired or improperly stored material can produce a coating that looks normal on the outside but has insufficient curing inside the winding.
After impregnation, the winding is held according to the regime specified by the material manufacturer and the process.
The following are monitored:
The air temperature in the oven and the temperature of the massive stator can differ significantly.
The surface can become dry before:
Insufficient curing leads to:
Overheating during drying can:
The regime must be controlled according to the process specification, not simply the operator’s experience.
For some windings, several cycles are applied:
The purpose:
However, more varnish does not always improve the result. An excess can block the ventilation ducts and impede cooling.
After curing, varnish is removed from surfaces where it must not remain:
The winding insulation must not be damaged during mechanical cleaning.
After drying and cooling, the following are carried out:
The purpose is to verify the dielectric strength of the insulation to the frame and between electrically separate circuits.
Before the test:
After the test, the winding is discharged and earthed.
The test voltage and duration must not be chosen arbitrarily. They depend on the rated voltage, the type of repair, the age of the insulation, the design and the applicable requirements.
Every test places an electrical stress on the insulation.
Repeating it without justification can:
A repeat test must be justified by the process, or by the need to confirm the repair.
The following are compared:
A difference may be linked to:
Before the rotor is fitted, or during a check with a reduced supply voltage, the following may be verified:
Such checks must be carried out using a safe circuit with current limiting.
Once testing is complete, the stator is incorporated into the overall assembly process.
Before inserting the rotor, the following are checked:
When fitting the rotor, contact with the winding must not be allowed to occur.
After assembly, the following are checked:
The test is started with a controlled regime and working protection.
Possible causes:
A high current should not be considered normal just because the motor turns.
The causes can be internal or external.
Internal:
External:
The currents and the phase voltages must be measured at the same time.
Possible causes:
Loud electromagnetic noise can be a sign of a serious error even when the insulation resistance is acceptable.
The main causes:
The thermal class of the materials does not eliminate the cause of excessive heat generation.
For critical machines, it is advisable to check:
Not every winding error is fully revealed at no load.
Energy efficiency can deteriorate because of:
A quality rewinding job should preserve the original electromagnetic characteristics as closely as possible.
Technically, this is possible in certain cases, but it requires an electromagnetic calculation.
The following must be checked:
A simple star-to-delta change does not always allow the motor to be converted to any other voltage.
Changing the number of poles changes the synchronous speed, but this is a rebuild, not an ordinary rewinding job.
The following must be assessed:
Not every motor can be safely converted to a different speed.
The power is limited not only by the winding but also by:
Increasing the wire cross-section by itself does not turn the motor into a higher-power machine.
For explosion-proof machines, the following are critical:
An arbitrary change to the winding data or the design can compromise the explosion protection.
The following are needed:
The quality of such a winding cannot be assessed with a megohmmeter and a test to the frame alone.
Dual-speed windings may have:
Before removal, it is especially important to:
Certain machines may have:
Such windings cannot be reproduced from a standard table alone.
| Observation | Possible cause | Recommended check |
|---|---|---|
| High current in all phases | Too few turns, a damaged core, high voltage | Check the turns, the diagram, the voltage and the core |
| High current in one phase | A connection error or a weak contact | Measure the resistance and check the groups |
| Loud hum | Incorrect polarity, air gap, rotor | Magnetic check, currents, air gap |
| Motor fails to reach speed | Incorrect diagram, rotor, insufficient torque | Check the connections and the rotor |
| Overheating at a connection | High contact resistance | Thermal and contact inspection |
| Local overheating of the stator | Core or a local winding defect | Thermal imaging, surge test |
| Low insulation resistance | Moisture, contamination, an impregnation defect | Drying and repeat measurements |
| Breakdown during testing | Damaged main insulation | Localisation and repair |
| Unequal phase resistance | Different turns, an open circuit in a parallel conductor | Check the diagram and the connections |
| Vibration at no load | Electromagnetic asymmetry or a mechanical defect | Spectrum analysis, currents, air gap, rotor |
| Smell of varnish after prolonged running | Insufficient curing or overheating | Temperature, drying regime |
| Loosening of the wedges | Incorrect size or shrinkage | Re-wedging |
| Sparking in the terminal box | A weak connection or damaged insulation | Inspection of the terminals and leads |
| Overheating when running from a frequency converter | Pulse loading or poor cooling | Check the insulation, filters and ventilation |
After removal, some of the parameters can no longer be reliably recovered.
It may have been rewound incorrectly before.
The enamel, the number of parallel conductors and the total copper cross-section must all be taken into account.
This raises the magnetic flux and the current.
The slot fill, the cooling and the geometry must be checked.
This can destroy the core.
A local hot spot will damage the new insulation.
The system may delaminate or fail to cure.
Even invisible damage to the enamel can become the site of a future short circuit.
Movement of the conductors destroys the insulation.
The motor can draw a dangerously high current.
After curing, correcting mistakes becomes far more difficult.
The oven temperature does not indicate the actual temperature of the winding.
This impairs cooling.
A full set of electrical and functional tests is required.
The correctness of the winding must be confirmed in the assembled machine.
It is necessary to check:
The elevated current should not be explained away simply as "the winding is new and has not yet bedded in."
Equal resistance does not guarantee:
Magnetic, surge and functional checks are required.
Possible causes:
The cause must be established before the high-voltage test.
Possible causes:
A smell should not automatically be considered normal for a new winding.
Possible causes:
The pattern of both failures and the operating conditions must be analysed.
The following are checked:
Causes:
Applying extra varnish on the surface does not always fix the underlying mechanical problem.
Record all the nameplate data and the operating conditions.
Determine the probable cause of the damage.
Insulation resistance, phase resistance, surge testing and other diagnostics.
Photographs and a description of each phase and zone.
Turns, pitch, wire, diagram, branches, geometry.
Before removing the old winding.
Without overheating or damaging the core.
Remove the insulation, varnish, copper and sharp edges.
Visually, thermally and electromagnetically.
If local defects are found.
Compare it with the nameplate, the calculation and similar machines.
As a single, compatible set.
Check the geometry of the end-turns.
With precise control of the turns and conductors.
Electrically and geometrically.
Without tears or sharp folds.
According to the diagram and the correct sequence.
At all the critical points.
With controlled tightness.
With the required clearances.
According to the verified diagram.
With materials of the appropriate class.
And check that they work correctly.
With the correct tension.
Diagram, resistance, polarity, insulation, surge test.
Until the condition of the insulation stabilises.
Using the chosen technology.
With monitoring of the actual temperature.
Without damaging the winding.
Including a dielectric-strength test.
With a check of the air gap.
Current, noise, vibration, temperature.
And keep the new winding data sheet on file.
| Stage | Main check | Documented result |
|---|---|---|
| Identification | Nameplate parameters | Motor record card |
| Failure analysis | The nature of the damage | Technical report |
| Data recording | Turns, pitch, wire, diagram | Winding data sheet |
| Removal | Temperature, core condition | Removal record |
| Cleaning | Slots, ducts, teeth | Inspection record |
| Core | Local losses, heating | Inspection report |
| Coils | Turns, resistance, geometry | Coil data sheet |
| Laying | Diagram, insulation, wedges | In-process control |
| Connections | Polarity, contact | Connection diagram |
| Before impregnation | Resistance, insulation, surge test | Interim report |
| Impregnation | Material, vacuum, pressure | Process log |
| Curing | Temperature, time | Temperature chart |
| Final check | Insulation, resistance, dielectric strength | Test report |
| No-load test | Currents, vibration, temperature | Test-bench report |
It is advisable to record:
Before handing the stator over for rewinding, it is advisable to provide:
After the repair, the following should be requested:
On site, the following must be checked:
It means fully or partially replacing its winding while restoring the electrical, mechanical and insulation parameters.
No. With limited, accessible damage, a local repair is possible, but only after assessing the overall condition of the insulation.
With diagnosing the cause of the failure and recording precise winding data.
It contains information about the number of turns, the pitch, the wire, the diagram and the geometry.
By direct counting, from factory documents, from a similar unit, or by calculation.
Not always. It may have been repaired incorrectly before.
Damage to the interlaminar insulation creates local losses and overheats the new winding.
Only using a controlled process that does not damage the core. An open flame and uncontrolled temperature are not acceptable.
It separates the winding from the earthed core and protects it mechanically.
They allow the conductors to move and wear away the insulation.
For dielectric strength, protection against moisture, heat transfer and mechanical fixing.
There is no universally best method. It depends on the type of machine, the voltage, the winding and the manufacturer’s requirements.
Not for every motor, but it improves the penetration of the material into densely wound coils.
It is a process in which air is removed from the winding under vacuum, after which the impregnating material is introduced under pressure.
Yes, if all the materials in the system are compatible. It does not correct calculation errors or poor cooling.
Only after checking the electromagnetic calculation, the slot fill and the thermal regime.
Arbitrarily — no. This can raise the magnetic flux and the current to a dangerous level.
To reveal interturn defects and asymmetry between windings.
No. A megohmmeter does not confirm the absence of an interturn short circuit or a diagram error.
To check the symmetry of the phases, the connections, the number of turns and the parallel conductors.
Because of incorrect group polarity, the diagram, the air gap, the core or the rotor.
Because of incorrect data, poor cooling, a damaged core, overload, or external supply problems.
Yes. It confirms that the winding performs correctly in the assembled motor.
For critical machines this is advisable, since not all defects appear without load.
Not always. The decision is made after cleaning, drying and a full set of insulation tests.
In some cases yes, but only after a full calculation.
By simply changing the wire — no. The power is limited by the entire design of the machine.
ELEKTROPROMREMONT LLC carries out a full range of work on the repair and rewinding of industrial electric motor stators.
The scope of work includes:
Stator rewinding is neither a mechanical copy of the old winding nor a simple replacement of the burnt-out wire.
A quality process must include:
A new winding must not merely fit into the slots and show a high insulation resistance. It must reproduce the calculated magnetic field, withstand the electrical and mechanical loads, and deliver the motor’s rated performance.
That is why the quality of a rewinding job is determined not by the outward appearance of the coils or the amount of varnish applied, but by the accuracy of the winding data, the condition of the core, the quality of the insulation system and the results of the full set of tests.
This material is for informational purposes. The values, diagnostic methods, scope of work and recommendations given here are general and do not replace the manufacturer’s technical documentation. The final decision for a specific machine is made from its own diagnostics and inspection, taking into account its type, power, design, duty, operating history and applicable standards.
We will carry out a full diagnosis of the cause of the failure, recover the winding data and perform the complete rewinding cycle — from manufacturing the coils to no-load testing.